Ongoing works at Fairham Pastures – Phase 1 of a new multi-use development

OVERVIEW

Works ongoing at Fairham Pastures – Phase 1 of a new multi-use development, consisting of new foul and surface water drainage.

S278 works to the existing road network, site wide service installations kerbs and footpaths installed.


We also installed as part of the main foul drainage works a section of 375mm dia pipe, 380m long at 9m deep – this involved extensive planning upfront to determine the safest and most economic way of completing the works whilst keeping within our clients programme.

PROJECT
Phase 1 Fairham Pastures


WORK UNDERTAKEN
Groundwork, Excavation, Infrastructure, Drainage, Kerbs, Footpaths


EQUIPTMENT USED
JCB 3Cx, 14T, 30T Excavators and 25T dumpers